Power supply to remain affected for a week in Budgam

1 min read
1000

Budgam, July 22: According to Superintending Engineer, EM&RE Circle IIND Srinagar, due to some technical
snag in 6.3 MVA Power transformer at Receiving Station Budgam, the entire load of the receiving station is

to be catered through a single 10 MVA power transformer, as such Power Supply to the metered feeders
namely Budgam town and JNV shall be restricted to 18 to 19 Hrs a day.
In non-metered feeders namely Jawalapora, Nasrullahpora, Bemina, Old Budgam and Shoolipora shall be
restricted to 11 to 12 Hrs a day.
This disruption shall remain till another 10 MVA power Transformer is installed within a week’s time. The
inconvenience to the general public is deeply regretted.